Austin: City plans light rail extension before breaking ground

Austin: City plans light rail extension before breaking ground

Austin started planning a three-mile light rail extension to Austin-Bergstrom International Airport, Planetizen reported. Construction on the first phase starts in 2027. The first phase will run 9.8 miles through the center of Austin.

It will go to the University of Texas at Austin and down South Congress. The partnership will work out the cost during the planning phase and will look into federal funding opportunities, Planetizen reported.

The airport extension is now part of the first phase, CultureMap reported. The mostly elevated line would run from the planned Yellow Jacket Station on East Riverside Drive.

Austin: City plans light rail extension before breaking ground
Photo: deeparrival.com

It would end at a planned station at the airport. Planning will take nine to 12 months, CultureMap reported.

Airport line joins first phase

Mayor Kirk Watson wrote about the plan in his Watson Wire newsletter on LinkedIn, CultureMap reported. “It’s time to start the process to get rail to the airport … An airport rail connection has been part of Austin’s long-term transportation vision for years,” Watson wrote.

The partnership confirmed the faster pace in a memo on Tuesday, CultureMap reported. The extension was listed as a preferred priority extension to come later. It was on a system map still live on the partnership website.

The partnership is speeding up planning for the extension, CultureMap reported. That will link it with other major work now underway in the region.

The top comment from residents during the environmental review was to extend light rail to the airport, CultureMap reported. Residents sought more travel choices and more reliable trips to the airport for passengers and the airport workforce.

Design work is underway on the airport’s \$5 billion expansion. Planning for the rail line and station must start now, CultureMap reported.

The airport is designing a new arrivals and departures hall. The partnership said it is critical that the hall be designed with light rail in mind. Dominique Leh reported that point for Fox 7 Austin.

System will cost roughly \$8 billion

The partnership is developing the light rail system for roughly \$8 billion. It is working with the Texas Department of Transportation and the Federal Transit Administration. They will fast-track approvals for the extension, CultureMap reported.

One line would run from a 38th Street station in North Central Austin, CultureMap reported. It would end at South Congress Avenue and East Oltorf Street.

The other line would run from a station just south of Lady Bird Lake to the airport station. The 38th Street line would have 10 stops, and the airport line would have six, CultureMap reported.

A second phase would extend the 38th Street line to the Crestview neighborhood in North Central Austin. In July, the partnership signed a deal with Stadler, a Swiss maker, to supply 21 train cars, CultureMap reported.

Each of the seven electric-powered trains will have five cars, and 16 stations will be built for the system. Each five-car train will hold about 240 passengers and travel up to 65 mph, CultureMap reported.

The first phase will have 15 stations linking Central, South and East Austin, Community Impact reported. It completed the federal environmental review in January. The first phase is expected to open in 2033, View from the Wing reported.

Cost and opening date not set

The extension has no set cost or schedule yet. A new federal environmental process is still to come, so any opening date is years away, Deep Arrival reported. The Federal Transit Administration has agreed to speed up its environmental review, View from the Wing reported.

The partnership is also looking at other options, including federal support. It will compare the extension’s cost and timing with existing projects and revenue, Community Impact reported.

Voters approved Project Connect, the wider transit plan, in 2020. They also backed a property tax increase, View from the Wing reported.

The original 2020 plan included an airport line, View from the Wing reported. It was later cut back from about 20 miles as costs rose. The airport link was dropped from the first phase.

The project also faces legal challenges over its financing structure. Those challenges remain in the courts, View from the Wing reported.

Mayor Kirk Watson said he hopes to deliver the extension within the budget voters already approved. That would use no new taxpayer dollars, Community Impact reported.

The airport is in the middle of its Journey With AUS expansion, Deep Arrival reported. The work includes a new terminal, a new concourse and rebuilt roads and parking.

The airport sold \$1.18 billion in bonds in May. It plans \$4.2 billion more through 2030, View from the Wing reported.

The airport link was earlier listed as a priority extension along US 183 and Highway 71. An airport spokesperson said the airport is preserving the right-of-way the line would need, Deep Arrival reported.

There is no rail service to the airport now, Deep Arrival reported. Travelers reach the airport by car, rideshare, taxi or the CapMetro Airport route.

That route runs between downtown and the terminal, Deep Arrival reported. Rideshare and taxi pickups require a walk through a parking garage, View from the Wing reported.